Hyde Park can proudly boast of its history and commitment to public education. Franklin Delano Roosevelt's father served on our Board of Education, and a local story tells that young Franklin had to mind his father's horse while Roosevelt, Sr. conducted school business. Years later, FDR built and dedicated two elementary schools and a brand new high school. This was accomplished through a combination of federal and local resources generated by his personal passion and belief in public education and his love for Hyde Park. Approximately sixty-five years ago these three schools were pro-gressive and "state-of-the-art."
Today, though still beautiful, they are worn and suffering from lack of attention to repair and upkeep. In this context it is incumbent upon us, the school staff and citizens of Hyde Park, to continue the legacy of FDR.
It is our civic and democratic responsibility to provide a quality education for Hyde Park's 21st century students. We can do no less than to become actively involved in the unending relay of human possibilities and to carry our grand history forward. We must do for our children what FDR and this community did for its students of Hyde Park sixty-five years ago.
In the Spring of 2003, a broad-based steering committee was established to re-view the key issues and needs surrounding facilities repair, renovation and possible ex-pansion due to current overcrowding (120% of capacity). The Hyde Park Facilities Steering Committee (HPFSC) met regularly to address all aspects of the problem and to identify possible solutions. Input was sought from citizens throughout the community. The Thomas Group, an architectural firm, was contracted to work with district staff to develop a comprehensive analysis of problems, needs and possible options.
In September 2004 the HPFSC narrowed these options to four. Estimated cost and the tax impacts were then calculated for financial modeling purposes only. Early in the process, goals and objectives were developed and used as guidelines throughout:
Key considerations were determined and discussed at length. No stone un-turned! No consideration undebated! These key issues were:
In the context of goals, objectives and key considerations, the Facilities Steering Committee gathered information, reviewed existing instructional programs, analyzed current building usage and overcrowded conditions, and considered the demographic study produced for the district by Western Suffolk BOCES. Community input was broad and deep.
Through a lengthy democratic process, fifteen options in four major categories were considered and agreed upon for further study and analysis:
| Code | Description |
|---|---|
| A. | "No-Build" status quo, alternative approaches |
| A-1. | Facilities "status quo" |
| A-2. | Year-round school |
| A-3. | Temporary space/modular classrooms |
| B. | Renovations to existing buildings ONLY |
| B-1. | Accessibility, health & safety |
| B-2. | Priority 1 items in all buildings |
| B-3. | Athletic fields, PE, site facilities district-wide |
| B-4. | Refurbish one building at a time |
| C. | Renovations + additions |
| C-1. | Current grade alignment K-5, 6-8, 9-12 |
| C-2. | K-4, 5-6, 7-8, 9-12 grade alignment |
| C-3. | K-4, 5-6, 7-9, 10-12 grade alignment |
| C-4. | Kindergarten center |
| C-5. | Tiered elementary K, 1-2 & 3-5 |
| D. | Renovations + additions + new facility |
| D-1. | New elementary school |
| D-2. | New high school |
| D-3. | New technology center & building |
On September 14, 2004 the HPFSC further reduced and modified these options based on positive educational advantages and cost:
| Code | Description |
|---|---|
| Option I: | ADA and life safety upgrade; |
| Option II: | Upgrade existing facilities that would include option I and build addi-tions to each school. (Grade-level configurations would remain the same.) |
| Option III: | Science, technology and arts major addition and FDR renovations that would include option I, plus renovations to all buildings. (Grade-level configuration: K-4, 5-6, 7-8, 9-12.) |
| Option IV: | New high school that would include option I and renovations to all buildings. (Grade-level configurations: K-3, 4-5, 6-7-8-, 9-12.) |
Pros and cons were listed for each option, as well as estimated cost for financial modeling purposes only. In every model and option, neighborhood schools and educa-tionally sound grade configurations and realignments were a prime consideration, along with financial impact.
All needs and associated cost estimates were based on current student enroll-ment (+/- 4,650) and included the projections of the demographic study done by West-ern Suffolk BOCES approximately two years ago. Based on the number of Hyde Park residential units permitted at that time, 600 additional students have been predicted to enroll in the Hyde Park Central School District over the next eight years.
The three-phased plan addresses the issues that the committee deemed important. The plan respects the historic character of the existing buildings. Long-range maintenance and repair programs have not been in place. All the district's buildings re-quire major renovations and alterations due to years of lack of attention. The committee agrees that "band aid" fixes are out of the question. All three phases place a priority on respecting the historic nature of the buildings, caring for existing buildings, and address-ing building deficiencies in their entirety.
The district has not been ADA compliant. The law required districts throughout the state to address accessibility concerns by July 1995. Phase one of the three-phase plan addresses accessibility issues throughout the district. The plan includes ramps to get into the buildings, as well as chair lifts and ramps. The committee understands the seriousness of noncompliance and the obligation to address all children's needs so that they can participate in all educational opportunities.
The district is struggling to meet education needs for the 21st century. Science and technology programs require specific learning spaces. Phase two includes science, technology, arts areas, and general instructional space.
The three-phase proposal supports neighborhood schools. The renovation of all schools, the restoration of the historic buildings, and construction of a 21st century learn-ing wing at FDR will meet the needs of 21st century students and bring a renewed pride to the community.
Presented by David Kuckuk, The Thomas Group
Each of the components of the Proposed Master Plan provides an overview of the committee's recommendation. The recommendation is truly a Master Plan and identifies how the district should address its educational facilities to support educational excellence in Hyde Park.
This recommendation is one of the most thoughtful approaches to master plan-ning that I have seen, avoiding the tendency to simply "do a building project," recogniz-ing that Hyde Park is in a dynamic, changing period and that an effective plan must not only provide answers to current issues but also must provide a framework for well-managed and cost-effective responses to future needs.
Several things are worth noting:
The Master Plan Recommendation falls into three components:
The three phases are overlapping, recognizing that they don't "stop and start" but occur in an ongoing way. The planning has been coordinated so that what is done in early phases supports future phases (i.e., so that nothing that is "done" needs to be "undone" in the future).
As the committee looked at the district's needs, it became apparent that some were more pressing, more urgent, than others. This first phase IS proposed as a build-ing project, as the needs are clearly defined. [refer to the extensive handout list.]
The proposed Phase 1 project would benefit every single building in the district, addressing the most immediate of these needs (although by no means all of them) in several broad areas:
To deal with these immediate needs, the committee recommends the Board con-sider a building project to be presented to the voters of the community as soon as pos-sible, perhaps as early as next March. If it were voted on at that time, some work could begin (after engineering, approvals, and bidding) as early as next fall and be completed by the end of 2006. Based on the list distributed out tonight, the project would have a total maximum (not-to-exceed) cost of $10.7 million, virtually all of which would be sub-ject to state building aid.
Phase 2 is the "BIG" piece of the Master Plan, as it establishes an educationally and fiscally sound model for how the district will use its facilities into the foreseeable future.
The HPCSD Facilities Steering Committee will continue its work immediately fol-lowing discussion and approval of the proposed recommendation by the HPCSD Board of Education. Though the committee's work over the past fifteen months has been long, arduous and, certainly, tedious at times, we have only just begun to all roll up our sleeves.
The scope and design of Phase 2 must be designed and developed. The pro-jected financing, tax and state aid impact must be clearly articulated. Simultaneously, continuous input from our schools and broader community must be sought systemati-cally and comprehensively.
Leaders from our five towns and school district must establish a working relation-ship and dialogue. A discussion of mutual concerns and benefits has to be ongoing, including the impact of residential growth and development.
As a whole community of which the HPCSD schools are essential and central, we are obligated to find the vision and will to carry forward the Roosevelt legacy. Our children deserve nothing less.
This phase of the Master Plan would address the Hyde Park Central School Districts immediate infrastructure needs, including upgrades for ADA, Health and Safety, and NYS Building Code violations at each building throughout the district.
A vote on a Bond Referendum to fund this phase will take place on Tuesday, March 15 at Haviland Middle School. The polls will be open from 6am until 9pm.
| Hyde Park Elementary School | |
| Corridor Separation - provide 1hr fire rated constr. to code | 62,500 |
| Door Closers - at fire rated doors - to code | 5,650 |
| Gym Wall Pads - on unprotected surfaces - health & safety | 9,000 |
| Floor Tile Replacement –Asbestos | 184,500 |
| Replace Fascia/Soffit, Correct Drainage at North Exit | 4,000 |
| Handicap Accessibility - stairs, signage, toilet rooms | 59,000" |
| Replace Acoustical Ceilings in Original Building | 32,000 |
| Replace existing Concrete Walk | 1,000 |
| New Parent Drop Off Parking | 50,000 |
| Security Lighting | 25,000 |
| Handicap Accessibility - new access ramps at building entrances | 45,000 |
| New Concrete Curb Cut - at playground for accessibility | 500 |
| Correct Drainage Problem at South Entry | 3,500 |
| Backflow Preventors - to protect potable water system - code | 11,500 |
| Correct Classroom Sinks with Bubblers - code | 6,000 |
| Kitchen Fire Suppression -code | 5,000 |
| Wrist Blades - code | 500 |
| Boiler Room Sump - existing needs replacing | 1,500 |
| Drain Pipe Testing | 1,000 |
| Water Coolers - Replacement - ADA code | 4,500 |
| Exit and Emergency Lighting - code | 2,300 |
| Smoke and Heat Detection - code | 73,000 |
| Fire Alarm System Replacement - ADA code | 58,700 |
| Clock System Replacement | 11,400 |
| Exterior Lighting Replacement | 4,700 |
| Convenience Receptacles | 41,400 |
| Handicap Accessibility - assistive listening, fire alarm bells & strobes | 27,890 |
| Sub Total Construction Cost | 731,040 |
| 10% Construction Contingency | 73,101 |
| 20% Incidental Budget | 160,828 |
| Hyde Park Elementary School Project Budget | 964,969 |
| Netherwood Elementary School | |
| Door Closers - at fire rated doors - to code | 9,400" |
| Floor Tile Replacement-Asbestos | 215,000 |
| Handicap Accessibility - stairs, signage, toilet rooms, platform lift | 102,800 |
| Reconstruct Asphalt Paving | 115,500 |
| Additional Site Lighting | 25,000 |
| Handicap Accessibility - accessible routes and ramps | 6,500 |
| New Parent Drop Off Loop | 50,000 |
| Correct Drainage at Playground | 5,000 |
| Backflow Preventors - to protect potable water system - code | 1,500 |
| Correct Classroom Sinks with Bubblers - code | 6,000 |
| Wrist Blades - code | 750 |
| Boiler Room Sump - existing needs replacing | 3,000 |
| Water Softener | 25,000 |
| New Domestic Water Well | 10,000 |
| Water Coolers - ADA code | 1,500 |
| Replace Clock System | 11,400 |
| Replace Exterior Lighting | 4,700 |
| Cafetorium Sound System | 12,500 |
| Convenience Receptacles | 31,400 |
| Handicap Accessibility - assistive listening devices | 5,500 |
| Sub Total Construction Cost | 642,450 |
| 10% Construction Contingency | 64,245 |
| 20% Incidental Budget | 141,339 |
| Netherwood Elementary School Project Budget | 848,034 |
| North Park Elementary School | |
| Door Closers - at fire rated doors - to code | 12,500 |
| Locker Room to Classroom Renovation - upgrade to code | 45,000 |
| Floor Tile Replacement-Asbestos | 33,400 |
| Handicap Accessibility - entrances, signage, and toilet rooms - ADA | 63,425 |
| New Asphalt Walks - connect to handicap ramp - ADA code | 3,500 |
| Additional Site Lighting | 25,000 |
| Restore Basketball Court | 9,500 |
| Handicap Accessibility - provide handicap parking - ADA code | 3,000 |
| Backflow Preventor - to protect potable water system - code | 1,500 |
| Boiler Room Eye Wash | 1,000 |
| Correct Classroom 124 Sinks with Bubbler - code | 3,000 |
| Replace Fuel Oil Pumps | 6,500 |
| Water Softener | 25,000 |
| Water Coolers - ADA code | 4,500 |
| Exit and Emergency Lights | 1,800 |
| Replace Service Transformers | 58,300 |
| Replace Sound System (includes Cafetorium) | 55,200 |
| Replace Clock System | 21,600 |
| Replace Exterior Lighting | 4,600 |
| Sub Total Construction Cost | 378,325 |
| 10% Construction Contingency | 37,833 |
| 20% Incidental Budget | 83,232 |
| North Park Elementary School Project Budget | 499,389 |
| Ralph R Smith Elementary School | |
| Correct Dead End Corridor - code | 42,000 |
| Floor Tile Replacement-Asbestos | 378,000 |
| Reconfigure Nurses Area - code | 15,000 |
| Abatement of Asbestos in Tunnels / Re-Insulate Piping | 208,000 |
| Ventilation to Boiler Room and Classroom Above | 40,000 |
| Handicap Accessibility - ADA code - Elevator, Stairlift | 201,060 |
| Removal of Existing Kitchen Wall - wall obstructs airflow through space | 2,800 |
| Reconstruct Existing Asphalt Paving | 190,300 |
| Additional Site Security Lighting | 25,000 |
| Correct Drainage Problem at Entrance Canopy | 1,000 |
| Backflow Preventor - to protect potable water system - code | 1,500 |
| Correct Classroom Sinks with Bubblers - code | 45,000 |
| Correct Abandoned Wells - code | 10,000 |
| Wrist Blades - ADA code | 400 |
| Vacuum Breakers - code | 400 |
| Replace Boiler Room Sump | 3,000 |
| Water Coolers - ADA code | 3,000 |
| Replace Water Distribution Piping Throughout Building - Asbestos | 160,000 |
| Exit and Emergency Lights - code | 2,400 |
| Smoke Detection / Heat Detection - code | 17,600 |
| Replace Fire Alarm System - code | 63,800 |
| Replace Clock System | 12,600 |
| Replace Exterior Lighting | 5,400 |
| Convenience Receptacles | 46,900 |
| Handicap Accessibilty - assistive listening, fire alarm bells & strobes - code | 28,700 |
| Sub Total Construction Cost | 1,503,860 |
| 10% Construction Contingency | 150,386 |
| 20% Incidental Budget | 330,849 |
| Ralph R. Smith Elementary School Project Budget | 1,985,095 |
| Violet Avenue Elementary School | |
| Coat Closet Replacement - health & safety - pivot type coat closets are a hazard | 76,000 |
| Door Closers - at fire rated doors - to code | 3,200 |
| Door Replacement-Cafeteria/Playroom/Gym - code | 20,800 |
| Stairwell Enclosure - code | 21,500 |
| Wall Pads in Gym - health & safety | 7,500 |
| Replace Flooring -Asbestos | 243,000 |
| Handicap Accessibility - ADA code - Elevator | 273,800 |
| Correct Drainage using French Drain and Removable Curb | 15,000 |
| Restoration of Asphalt Paving at Parking and Playground | 50,400 |
| Provide Additional Site Security Lighting | 25,000 |
| Replace Asphalt Paving at Service Area | 22,000 |
| Handicap Accessibility - to playground - ADA code | 8,000 |
| Correct Drainage Problem at North Entrance | 1,000 |
| Replace Boiler Room Sump | 1,500 |
| Water Coolers - ADA code | 6,000 |
| Exit Lights - code | 1,300 |
| Fire Alarm Pull Stations at Stair No. 2 - code | 500 |
| Smoke Detection / Heat Detection -code | 14,600 |
| Replace Fire Alarm System - code | 64,800 |
| Replace Sound System including Gym/Auditorium/Music Room | 58,000 |
| Additional Exterior Lighting – Teacher Parking | 6,700 |
| Power Panels and Circuit Wiring | 49,900 |
| Convenience Receptacles | 32,200 |
| Handicap Accessibilty - fire alarm bells & strobes - ADA code | 22,600 |
| Sub Total Construction Cost | 1,025,300 |
| 10% Construction Contingency | 102,530 |
| 20% Incidental Budget | 225,566 |
| Violet Avenue Elementary School Project Budget | 1,353,396 |
| Haviland Middle School | |
| Door Closers - at fire rated doors - to code | 10,950 |
| Corridor Seperation (ventilation) - provide 1hr fire rated constr. - code | 55,000 |
| Exiting – Assembly at Library - code | 7,250 |
| Stair Enclosures - code | 56,250 |
| Replace Wall Pads in Gym - health & safety | 7,200 |
| Replace Flooring -Asbestos | 407,000 |
| Replace Gym Folding Partition | 68,750 |
| Partial Roof Replacement | 199,488 |
| Handicap Accessibility - ADA code- Elevator | 237,300 |
| Restoration of Asphalt Paving and Basketball Courts | 180,200 |
| Provide Additional Security Lighting at Parking and Pedestrian Areas | 25,000 |
| Handicap Accessibility - provide ramps at entrances - ADA code | 20,000 |
| Backflow Preventor - to protect potable water system - code | 1,500 |
| Replace Boiler Room Sump | 5,000 |
| Water Coolers - ADA code | 13,500 |
| Replace Fuel Oil Pumps | 6,500 |
| Water Tank Removal | 5,000 |
| Water Softener System | 35,000 |
| Replace Piping in Floors | N/A> |
| Exit Lights - code | 400 |
| Fire Alarm Pull Stations at Exit near Home Ec - code | 500 |
| Smoke Detection / Heat Detection - code | 23,300 |
| Replace Cloth Wire | 145,800 |
| Replacement of Gym and Auditorium Sound Systems | 41,000 |
| Replace Main Distribution Panel | 38,700 |
| Electric Panel Replacement | 45,300 |
| Power Panels and Circuit Wiring | 46,200 |
| Convenience Receptacles | 38,300 |
| Handicap Accessibilty - assistive listening, fire alarm bells & strobes - ADA code | 35,800 |
| Sub Total Construction Cost | 1,756,188 |
| 10% Construction Contingency | 175,619 |
| 20% Incidental Budget | 386,361 |
| Haviland Middle School Project Budget | 2,318,168 |
| FD Roosevelt High School | |
| Door Closers - at fire rated doors - to code | 31,250 |
| Stair Enclosures - code | 134,000 |
| Replace Flooring -Asbestos | 395,200 |
| Floor Replacement – Parquet | 53,300 |
| Gym Floor Refinishing | 48,800 |
| Floor – Carpet Replacement with Linoleum | 68,400 |
| Locker Rooms – Locker Replacement | 94,000 |
| Handicap Accessibility - ADA code | 112,050 |
| Replace Gym Folding Partition | 137,500 |
| Additional Security Lighting | 25,000 |
| Handicap Accessibility - ADA code | 10,000 |
| Provide Additional Ventilation at Auditorium | 150,000 |
| Replace 3 Boiler Burners | 35,000 |
| Backflow Preventor - to protect potable water system - code | 1,500 |
| Wrist Blades - ADA code | 300 |
| Vacuum Breakers - code | 600 |
| Replace Dark Room Faucet with Vacuum Breaker Type - code | 1,000 |
| Kitchen Fire Suppression Valve - code | 2,000 |
| Replace Boiler Room Sump | 2,000 |
| Replace Fuel Oil Transfer Pumps | 6,500 |
| Replace Water System Air Compressor (Autocon System) | 2,500 |
| Water Coolers - ADA code | 28,500 |
| Replace Sewage Ejector Pump System | 10,000 |
| Replace Domestic Water Mains – Lead | 300,000 |
| Exit Lights - code | 2,400 |
| Fire Alarm Pull Stations at Exit near Clrm 125. - code | 500 |
| Smoke Detection / Heat Detection - code | 36,000 |
| Replace Fire Alarm System - code | 157,900 |
| Replace Clock System | 42,200 |
| Keyless Entry System | 19,800 |
| Replace Sound System including Gymnasium | 93,100 |
| Replace Exterior Lighting | 12,300 |
| Handicap Accessibilty - assistive listening, fire alarm bells & strobes - ADA code | 55,300 |
| Sub Total Construction Cost | 2,068,900 |
| 10% Construction Contingency | 206,890 |
| 20% Incidental Budget | 455,158 |
| F.D. Roosevelt High School Project Budget | 2,730,948 |
This phase of the Master Plan would address the Facilities, Program, and Enrollment needs at the Hyde Park Central School District elementary school buildings. The existing grade levels would be reconfigured to K-4, with renovations / alterations work taking place as follows:
This phase of the Master Plan would address the Facilities, Program, and Enrollment needs at the Haviland Middle School building. The existing grade level would be reconfigured to 5-6, with renovations / alterations work taking place as follows:
This phase of the Master Plan would address the Facilities, Program, and Enrollment needs at the F.D. Roosevelt building. The renovations would work in concert with the additions in Phase 2d to create a 7,8, and 9-12 grade Science, Technology, and Arts Center. The existing grade level would be reconfigured to 7-8, with renovations / alterations work taking place as follows:
This phase of the Master Plan would address the Facilities, Program, and Enrollment needs at the F.D. Roosevelt building. The additions would work in concert with the alterations in Phase 2c to create a 7,8, and 9-12 grade Science, Technology, and Arts Center.
This phase of the Master Plan would address a long-term space solution to house the Hyde Park Central School District.