Hyde Park Central School District

Facilities Master Plan Steering Committee Report

Presented to the Hyde Park Central School District Board of Education

December 9, 2004

Carole A. Pickering, Superintendent of Schools

Lorelei Case, Assistant Superintendent for Business

David Kuckuk, and Matthew Monaghan, The Thomas Group

I. History and Overview

Hyde Park can proudly boast of its history and commitment to public education. Franklin Delano Roosevelt's father served on our Board of Education, and a local story tells that young Franklin had to mind his father's horse while Roosevelt, Sr. conducted school business. Years later, FDR built and dedicated two elementary schools and a brand new high school. This was accomplished through a combination of federal and local resources generated by his personal passion and belief in public education and his love for Hyde Park. Approximately sixty-five years ago these three schools were pro-gressive and "state-of-the-art."

Today, though still beautiful, they are worn and suffering from lack of attention to repair and upkeep. In this context it is incumbent upon us, the school staff and citizens of Hyde Park, to continue the legacy of FDR.

It is our civic and democratic responsibility to provide a quality education for Hyde Park's 21st century students. We can do no less than to become actively involved in the unending relay of human possibilities and to carry our grand history forward. We must do for our children what FDR and this community did for its students of Hyde Park sixty-five years ago.

In the Spring of 2003, a broad-based steering committee was established to re-view the key issues and needs surrounding facilities repair, renovation and possible ex-pansion due to current overcrowding (120% of capacity). The Hyde Park Facilities Steering Committee (HPFSC) met regularly to address all aspects of the problem and to identify possible solutions. Input was sought from citizens throughout the community. The Thomas Group, an architectural firm, was contracted to work with district staff to develop a comprehensive analysis of problems, needs and possible options.

II. Goals & Objectives

In September 2004 the HPFSC narrowed these options to four. Estimated cost and the tax impacts were then calculated for financial modeling purposes only. Early in the process, goals and objectives were developed and used as guidelines throughout:

  1. To produce a long range comprehensive facilities plan that would provide guidance in major renovations of our existing buildings and new instructional fa-cilities;
  2. To consider appropriate instructional space for the educational process as the community experiences student-community growth;
  3. To consider and support equitable programming for all students throughout our school district
  4. To consider specific physical facilities that promote student learning and par-ticipation in science, instructional technology, fine arts and athletics.
  5. To provide safe and secure learning facilities for students, employees and parents;
  6. To provide a process/opportunity for all interested community members to participate in the planning and design process of this master facilities project;
  7. To provide and encourage a process that is mindful of the fiscal realities of this community and its taxpayers.

III. Key Considerations

Key considerations were determined and discussed at length. No stone un-turned! No consideration undebated! These key issues were:

  1. Educational program needed for 21st century students (learning standards, resources, opportunities, and space requirements);
  2. Handicapped accessibility in all buildings;
  3. Cost/tax impact;
  4. Benefits for citizens and the community;
  5. Maintenance of the FDR era schools and the age of buildings;
  6. Demographics: Current overcrowding and future needs based on residen-tial development and the Western Suffolk BOCES Demographic Study;
  7. Grade Configuration (all options considered from both academic and "neighborhood schools" perspective;
  8. Minimal redistricting (desire for least disruption);
  9. Positive impact on overall educational program.

IV. Master Planning Process

In the context of goals, objectives and key considerations, the Facilities Steering Committee gathered information, reviewed existing instructional programs, analyzed current building usage and overcrowded conditions, and considered the demographic study produced for the district by Western Suffolk BOCES. Community input was broad and deep.

Through a lengthy democratic process, fifteen options in four major categories were considered and agreed upon for further study and analysis:

CodeDescription
A. "No-Build" status quo, alternative approaches
A-1. Facilities "status quo"
A-2. Year-round school
A-3. Temporary space/modular classrooms
B. Renovations to existing buildings ONLY
B-1. Accessibility, health & safety
B-2. Priority 1 items in all buildings
B-3. Athletic fields, PE, site facilities district-wide
B-4. Refurbish one building at a time
C. Renovations + additions
C-1. Current grade alignment K-5, 6-8, 9-12
C-2. K-4, 5-6, 7-8, 9-12 grade alignment
C-3. K-4, 5-6, 7-9, 10-12 grade alignment
C-4. Kindergarten center
C-5. Tiered elementary K, 1-2 & 3-5
D. Renovations + additions + new facility
D-1. New elementary school
D-2. New high school
D-3. New technology center & building
Initial set of facilities options considered by the Facilities Steering Committee

On September 14, 2004 the HPFSC further reduced and modified these options based on positive educational advantages and cost:

CodeDescription
Option I: ADA and life safety upgrade;
Option II: Upgrade existing facilities that would include option I and build addi-tions to each school. (Grade-level configurations would remain the same.)
Option III: Science, technology and arts major addition and FDR renovations that would include option I, plus renovations to all buildings. (Grade-level configuration: K-4, 5-6, 7-8, 9-12.)
Option IV: New high school that would include option I and renovations to all buildings. (Grade-level configurations: K-3, 4-5, 6-7-8-, 9-12.)
Final set of facilities options considered by the Facilities Steering Committee

Pros and cons were listed for each option, as well as estimated cost for financial modeling purposes only. In every model and option, neighborhood schools and educa-tionally sound grade configurations and realignments were a prime consideration, along with financial impact.

All needs and associated cost estimates were based on current student enroll-ment (+/- 4,650) and included the projections of the demographic study done by West-ern Suffolk BOCES approximately two years ago. Based on the number of Hyde Park residential units permitted at that time, 600 additional students have been predicted to enroll in the Hyde Park Central School District over the next eight years.

V. Proposed Three-Phase Plan

The three-phased plan addresses the issues that the committee deemed important. The plan respects the historic character of the existing buildings. Long-range maintenance and repair programs have not been in place. All the district's buildings re-quire major renovations and alterations due to years of lack of attention. The committee agrees that "band aid" fixes are out of the question. All three phases place a priority on respecting the historic nature of the buildings, caring for existing buildings, and address-ing building deficiencies in their entirety.

The district has not been ADA compliant. The law required districts throughout the state to address accessibility concerns by July 1995. Phase one of the three-phase plan addresses accessibility issues throughout the district. The plan includes ramps to get into the buildings, as well as chair lifts and ramps. The committee understands the seriousness of noncompliance and the obligation to address all children's needs so that they can participate in all educational opportunities.

The district is struggling to meet education needs for the 21st century. Science and technology programs require specific learning spaces. Phase two includes science, technology, arts areas, and general instructional space.

The three-phase proposal supports neighborhood schools. The renovation of all schools, the restoration of the historic buildings, and construction of a 21st century learn-ing wing at FDR will meet the needs of 21st century students and bring a renewed pride to the community.

VI. Proposed Master Plan Recommendation

Presented by David Kuckuk, The Thomas Group

Each of the components of the Proposed Master Plan provides an overview of the committee's recommendation. The recommendation is truly a Master Plan and identifies how the district should address its educational facilities to support educational excellence in Hyde Park.

This recommendation is one of the most thoughtful approaches to master plan-ning that I have seen, avoiding the tendency to simply "do a building project," recogniz-ing that Hyde Park is in a dynamic, changing period and that an effective plan must not only provide answers to current issues but also must provide a framework for well-managed and cost-effective responses to future needs.

Several things are worth noting:

The Master Plan Recommendation falls into three components:

  • Phase 1 recognizes that there are needs to be addressed NOW - in fact they are probably overdue to be addressed. These include addressing issues of handicapped accessibility (ADA ) and maintaining a safe environment in the Hyde Park Schools. This phase of the Master Plan Recommendation is defined as a Building Project, as the needs are very clear and readily definable.
  • Phase 2 is the heart of the Master Plan. It proposed a way to use district facili-ties that is educationally sound, addresses current needs, moves the district into the future based on current, realistic data (not "pie-in-the-sky" projections) and allows flexibil-ity for the district in the future as other needs and supporting data become clearer. To-day it is presented as a "Model" or "Framework," not a building project. It is, however, defined enough so that, if the Board chooses to move ahead in this direction, it can be confidently developed into a project or series of projects.
  • Phase 3 recognizes that, while we can do some forecasting, we cannot predict the future. The best way to avoid potential overbuilding or using bad information today is to continue the planning process into the future. This way the district can continue to monitor development and growth, coordinate with other town and local needs, and plan to address future needs in a coordinated, well-planned, and cost-effective manner.
  • The three phases are overlapping, recognizing that they don't "stop and start" but occur in an ongoing way. The planning has been coordinated so that what is done in early phases supports future phases (i.e., so that nothing that is "done" needs to be "undone" in the future).

    As the committee looked at the district's needs, it became apparent that some were more pressing, more urgent, than others. This first phase IS proposed as a build-ing project, as the needs are clearly defined. [refer to the extensive handout list.]

    Phase 1

    The proposed Phase 1 project would benefit every single building in the district, addressing the most immediate of these needs (although by no means all of them) in several broad areas:

    To deal with these immediate needs, the committee recommends the Board con-sider a building project to be presented to the voters of the community as soon as pos-sible, perhaps as early as next March. If it were voted on at that time, some work could begin (after engineering, approvals, and bidding) as early as next fall and be completed by the end of 2006. Based on the list distributed out tonight, the project would have a total maximum (not-to-exceed) cost of $10.7 million, virtually all of which would be sub-ject to state building aid.

    Phase 2

    Phase 2 is the "BIG" piece of the Master Plan, as it establishes an educationally and fiscally sound model for how the district will use its facilities into the foreseeable future.

    VII. Where Do We Go From Here?

    The HPCSD Facilities Steering Committee will continue its work immediately fol-lowing discussion and approval of the proposed recommendation by the HPCSD Board of Education. Though the committee's work over the past fifteen months has been long, arduous and, certainly, tedious at times, we have only just begun to all roll up our sleeves.

    The scope and design of Phase 2 must be designed and developed. The pro-jected financing, tax and state aid impact must be clearly articulated. Simultaneously, continuous input from our schools and broader community must be sought systemati-cally and comprehensively.

    Leaders from our five towns and school district must establish a working relation-ship and dialogue. A discussion of mutual concerns and benefits has to be ongoing, including the impact of residential growth and development.

    As a whole community of which the HPCSD schools are essential and central, we are obligated to find the vision and will to carry forward the Roosevelt legacy. Our children deserve nothing less.

    HPCSD Master Plan Phase Description

    October 28, 2004

    PHASE 1 - ADA / Health and Safety Upgrades $10,700,000

    This phase of the Master Plan would address the Hyde Park Central School Districts immediate infrastructure needs, including upgrades for ADA, Health and Safety, and NYS Building Code violations at each building throughout the district.

    A vote on a Bond Referendum to fund this phase will take place on Tuesday, March 15 at Haviland Middle School. The polls will be open from 6am until 9pm.

    Hyde Park Elementary School
    Corridor Separation - provide 1hr fire rated constr. to code62,500
    Door Closers - at fire rated doors - to code 5,650
    Gym Wall Pads - on unprotected surfaces - health & safety 9,000
    Floor Tile Replacement –Asbestos 184,500
    Replace Fascia/Soffit, Correct Drainage at North Exit4,000
    Handicap Accessibility - stairs, signage, toilet rooms59,000"
    Replace Acoustical Ceilings in Original Building 32,000
    Replace existing Concrete Walk 1,000
    New Parent Drop Off Parking 50,000
    Security Lighting 25,000
    Handicap Accessibility - new access ramps at building entrances 45,000
    New Concrete Curb Cut - at playground for accessibility500
    Correct Drainage Problem at South Entry 3,500
    Backflow Preventors - to protect potable water system - code 11,500
    Correct Classroom Sinks with Bubblers - code 6,000
    Kitchen Fire Suppression -code 5,000
    Wrist Blades - code 500
    Boiler Room Sump - existing needs replacing 1,500
    Drain Pipe Testing 1,000
    Water Coolers - Replacement - ADA code 4,500
    Exit and Emergency Lighting - code 2,300
    Smoke and Heat Detection - code 73,000
    Fire Alarm System Replacement - ADA code 58,700
    Clock System Replacement 11,400
    Exterior Lighting Replacement 4,700
    Convenience Receptacles 41,400
    Handicap Accessibility - assistive listening, fire alarm bells & strobes27,890
    Sub Total Construction Cost 731,040
    10% Construction Contingency 73,101
    20% Incidental Budget 160,828
    Hyde Park Elementary School Project Budget 964,969
    Netherwood Elementary School
    Door Closers - at fire rated doors - to code9,400"
    Floor Tile Replacement-Asbestos 215,000
    Handicap Accessibility - stairs, signage, toilet rooms, platform lift102,800
    Reconstruct Asphalt Paving 115,500
    Additional Site Lighting 25,000
    Handicap Accessibility - accessible routes and ramps 6,500
    New Parent Drop Off Loop 50,000
    Correct Drainage at Playground 5,000
    Backflow Preventors - to protect potable water system - code 1,500
    Correct Classroom Sinks with Bubblers - code 6,000
    Wrist Blades - code750
    Boiler Room Sump - existing needs replacing 3,000
    Water Softener 25,000
    New Domestic Water Well 10,000
    Water Coolers - ADA code 1,500
    Replace Clock System 11,400
    Replace Exterior Lighting 4,700
    Cafetorium Sound System 12,500
    Convenience Receptacles 31,400
    Handicap Accessibility - assistive listening devices 5,500
    Sub Total Construction Cost 642,450
    10% Construction Contingency 64,245
    20% Incidental Budget 141,339
    Netherwood Elementary School Project Budget 848,034
    North Park Elementary School
    Door Closers - at fire rated doors - to code12,500
    Locker Room to Classroom Renovation - upgrade to code 45,000
    Floor Tile Replacement-Asbestos 33,400
    Handicap Accessibility - entrances, signage, and toilet rooms - ADA63,425
    New Asphalt Walks - connect to handicap ramp - ADA code 3,500
    Additional Site Lighting 25,000
    Restore Basketball Court 9,500
    Handicap Accessibility - provide handicap parking - ADA code 3,000
    Backflow Preventor - to protect potable water system - code 1,500
    Boiler Room Eye Wash 1,000
    Correct Classroom 124 Sinks with Bubbler - code 3,000
    Replace Fuel Oil Pumps 6,500
    Water Softener 25,000
    Water Coolers - ADA code 4,500
    Exit and Emergency Lights 1,800
    Replace Service Transformers 58,300
    Replace Sound System (includes Cafetorium) 55,200
    Replace Clock System 21,600
    Replace Exterior Lighting 4,600
    Sub Total Construction Cost 378,325
    10% Construction Contingency 37,833
    20% Incidental Budget 83,232
    North Park Elementary School Project Budget499,389
    Ralph R Smith Elementary School
    Correct Dead End Corridor - code42,000
    Floor Tile Replacement-Asbestos 378,000
    Reconfigure Nurses Area - code 15,000
    Abatement of Asbestos in Tunnels / Re-Insulate Piping 208,000
    Ventilation to Boiler Room and Classroom Above 40,000
    Handicap Accessibility - ADA code - Elevator, Stairlift201,060
    Removal of Existing Kitchen Wall - wall obstructs airflow through space 2,800
    Reconstruct Existing Asphalt Paving 190,300
    Additional Site Security Lighting 25,000
    Correct Drainage Problem at Entrance Canopy 1,000
    Backflow Preventor - to protect potable water system - code 1,500
    Correct Classroom Sinks with Bubblers - code 45,000
    Correct Abandoned Wells - code 10,000
    Wrist Blades - ADA code400
    Vacuum Breakers - code400
    Replace Boiler Room Sump 3,000
    Water Coolers - ADA code 3,000
    Replace Water Distribution Piping Throughout Building - Asbestos 160,000
    Exit and Emergency Lights - code 2,400
    Smoke Detection / Heat Detection - code 17,600
    Replace Fire Alarm System - code 63,800
    Replace Clock System 12,600
    Replace Exterior Lighting 5,400
    Convenience Receptacles 46,900
    Handicap Accessibilty - assistive listening, fire alarm bells & strobes - code28,700
    Sub Total Construction Cost 1,503,860
    10% Construction Contingency 150,386
    20% Incidental Budget 330,849
    Ralph R. Smith Elementary School Project Budget 1,985,095
    Violet Avenue Elementary School
    Coat Closet Replacement - health & safety - pivot type coat closets are a hazard76,000
    Door Closers - at fire rated doors - to code 3,200
    Door Replacement-Cafeteria/Playroom/Gym - code 20,800
    Stairwell Enclosure - code 21,500
    Wall Pads in Gym - health & safety 7,500
    Replace Flooring -Asbestos 243,000
    Handicap Accessibility - ADA code - Elevator 273,800
    Correct Drainage using French Drain and Removable Curb 15,000
    Restoration of Asphalt Paving at Parking and Playground 50,400
    Provide Additional Site Security Lighting 25,000
    Replace Asphalt Paving at Service Area 22,000
    Handicap Accessibility - to playground - ADA code 8,000
    Correct Drainage Problem at North Entrance 1,000
    Replace Boiler Room Sump 1,500
    Water Coolers - ADA code 6,000
    Exit Lights - code 1,300
    Fire Alarm Pull Stations at Stair No. 2 - code500
    Smoke Detection / Heat Detection -code 14,600
    Replace Fire Alarm System - code 64,800
    Replace Sound System including Gym/Auditorium/Music Room 58,000
    Additional Exterior Lighting – Teacher Parking 6,700
    Power Panels and Circuit Wiring 49,900
    Convenience Receptacles 32,200
    Handicap Accessibilty - fire alarm bells & strobes - ADA code 22,600
    Sub Total Construction Cost 1,025,300
    10% Construction Contingency 102,530
    20% Incidental Budget 225,566
    Violet Avenue Elementary School Project Budget 1,353,396
    Haviland Middle School
    Door Closers - at fire rated doors - to code10,950
    Corridor Seperation (ventilation) - provide 1hr fire rated constr. - code 55,000
    Exiting – Assembly at Library - code 7,250
    Stair Enclosures - code 56,250
    Replace Wall Pads in Gym - health & safety 7,200
    Replace Flooring -Asbestos 407,000
    Replace Gym Folding Partition 68,750
    Partial Roof Replacement 199,488
    Handicap Accessibility - ADA code- Elevator 237,300
    Restoration of Asphalt Paving and Basketball Courts 180,200
    Provide Additional Security Lighting at Parking and Pedestrian Areas 25,000
    Handicap Accessibility - provide ramps at entrances - ADA code 20,000
    Backflow Preventor - to protect potable water system - code 1,500
    Replace Boiler Room Sump 5,000
    Water Coolers - ADA code 13,500
    Replace Fuel Oil Pumps 6,500
    Water Tank Removal 5,000
    Water Softener System 35,000
    Replace Piping in FloorsN/A>
    Exit Lights - code400
    Fire Alarm Pull Stations at Exit near Home Ec - code 500
    Smoke Detection / Heat Detection - code 23,300
    Replace Cloth Wire 145,800
    Replacement of Gym and Auditorium Sound Systems 41,000
    Replace Main Distribution Panel 38,700
    Electric Panel Replacement 45,300
    Power Panels and Circuit Wiring 46,200
    Convenience Receptacles 38,300
    Handicap Accessibilty - assistive listening, fire alarm bells & strobes - ADA code35,800
    Sub Total Construction Cost 1,756,188
    10% Construction Contingency 175,619
    20% Incidental Budget 386,361
    Haviland Middle School Project Budget 2,318,168
    FD Roosevelt High School
    Door Closers - at fire rated doors - to code31,250
    Stair Enclosures - code 134,000
    Replace Flooring -Asbestos 395,200
    Floor Replacement – Parquet 53,300
    Gym Floor Refinishing 48,800
    Floor – Carpet Replacement with Linoleum 68,400
    Locker Rooms – Locker Replacement 94,000
    Handicap Accessibility - ADA code 112,050
    Replace Gym Folding Partition 137,500
    Additional Security Lighting 25,000
    Handicap Accessibility - ADA code 10,000
    Provide Additional Ventilation at Auditorium 150,000
    Replace 3 Boiler Burners 35,000
    Backflow Preventor - to protect potable water system - code 1,500
    Wrist Blades - ADA code300
    Vacuum Breakers - code600
    Replace Dark Room Faucet with Vacuum Breaker Type - code 1,000
    Kitchen Fire Suppression Valve - code 2,000
    Replace Boiler Room Sump 2,000
    Replace Fuel Oil Transfer Pumps 6,500
    Replace Water System Air Compressor (Autocon System) 2,500
    Water Coolers - ADA code 28,500
    Replace Sewage Ejector Pump System 10,000
    Replace Domestic Water Mains – Lead 300,000
    Exit Lights - code 2,400
    Fire Alarm Pull Stations at Exit near Clrm 125. - code500
    Smoke Detection / Heat Detection - code 36,000
    Replace Fire Alarm System - code 157,900
    Replace Clock System 42,200
    Keyless Entry System 19,800
    Replace Sound System including Gymnasium 93,100
    Replace Exterior Lighting 12,300
    Handicap Accessibilty - assistive listening, fire alarm bells & strobes - ADA code55,300
    Sub Total Construction Cost 2,068,900
    10% Construction Contingency 206,890
    20% Incidental Budget 455,158
    F.D. Roosevelt High School Project Budget 2,730,948

    PHASE 2 DISTRICT WIDE FACILITIES, PROGRAM, and ENROLLMENT UPGRADES

    PHASE 2a - Existing Elementary Buildings - Renovations

    This phase of the Master Plan would address the Facilities, Program, and Enrollment needs at the Hyde Park Central School District elementary school buildings. The existing grade levels would be reconfigured to K-4, with renovations / alterations work taking place as follows:

    Violet Avenue Elementary School

    R.R. Smith Elementary School

    North Park Elementary School

    Netherwood Elementary School

    Hyde Park Elementary School

    Return
to HPCSD HomeReturn to HPCSD Home Page BackBack
    Send email to the WebMaster
    This page has been visited 1932 times since Fri Dec 10 10:41:46 2004, most recently at Tue Apr 3 09:55:30 2007..
    Last updated Monday, 07-Nov-2005 17:16:23 EST